Phase 2 Schedule: Preliminary Engineering & Design
Task | Description | Timeframe |
---|---|---|
1 | Data Collection
| July to August, 2018 |
2 | Preliminary Engineering Design
| September 2018 to May 2019 |
3 | Regulatory Permitting
| August 2018 to October 2019 |
4 | Public/Stakeholder Involvement
| Ongoing with large emphasis during the preliminary design and permitting tasks. |
Phase 1 Schedule: Study
Task | Description | Timeframe |
---|---|---|
1 | Study Work Plan & Public Outreach Plan Development, Data Collection, Criteria Development | March 1 to mid-May, 2017 |
2 | Analysis of Existing Conditions | April to mid-June, 2017 |
3 | Alternatives Development & Evaluation | Mid-June to September, 2017 |
4 | Finalization of Study & Reporting | September to February, 2018 |