Priest Lake Water Management Project Schedule

Phase 4 Schedule: Construction Improvements

     Outlet Thorofare
  • Construction Complete – Spring 2020

     Outlet Dam 
  •  Phase 1 Construction – Winter 2020/2021 & Winter 2021/2022
  •  Phase 2 Construction – Anticipated to begin November 2023

 

Phase 3 Schedule: Engineering Design & Preparation of Construction Documents

  • Construction documents completed summer 2020

 

Phase 2 Schedule: Preliminary Engineering & Design

Task Description Timeframe
1

Data Collection

  • Kickoff Meeting
  • Existing & New Data Collection
  • Site Assessments — dam, wetlands, erosion areas on lake, Thorofare
  • Design Recommendations — refinement of recommendations from Phase 1 and any new information gathered that could affect the scope of preliminary design
  • Basis of Design — refinement and update from Phase 1
  • Steering Committee Meeting #1 — late August
July to August, 2018
2

Preliminary Engineering Design

  • Regulator Agency & Stakeholder Engagement
  • Steering Committee Meeting #2 — November 2018
  • Public Meeting/Open House — late September 2018
  • Permitting Level Plans — draft March; final April
  • Updated Construction Cost Estimates — draft April
  • Dam Improvements & Dam Safety Report Submittal — includes discipline reports (geotechnical, structural, hydraulic, and so forth) — March
September 2018 to May 2019
3

Regulatory Permitting

  • Consultation with Agencies regarding proposed concepts — September 2018
  • Permit Application Documents — initiate development of documents starting in September and working through Spring 2019
  • Permit Application Submission — Spring 2019
August 2018 to October 2019
4

Public/Stakeholder Involvement

  • Steering Committee Meeting #1 — late August 2018 (in person)
  • Steering Committee Meeting #2 — mid-September 2018 (telecon)
  • Public Meeting/Open House — late September 2018 (in person, Priest Lake)
  • Steering Committee Meeting #3 — October 2018
  • Steering Committee Meeting #4 — November 2018
  • Steering Committee Meeting #5 — July 2019
Ongoing with large emphasis during the preliminary design and permitting tasks.

Phase 1 Schedule: Study

Task Description Timeframe
1 Study Work Plan & Public Outreach Plan Development, Data Collection, Criteria Development March 1 to mid-May, 2017
2 Analysis of Existing Conditions April to mid-June, 2017
3 Alternatives Development & Evaluation Mid-June to September, 2017
4 Finalization of Study & Reporting September to February, 2018