Phase 4 Schedule: Construction Improvements
Outlet Thorofare
-
Construction Complete – Spring 2020
Outlet Dam
- Phase 1 Construction – Winter 2020/2021 & Winter 2021/2022
- Phase 2 Construction – Anticipated to begin November 2023
Phase 3 Schedule: Engineering Design & Preparation of Construction Documents
- Construction documents completed summer 2020
Phase 2 Schedule: Preliminary Engineering & Design
Task | Description | Timeframe |
---|---|---|
1 |
Data Collection
|
July to August, 2018 |
2 |
Preliminary Engineering Design
|
September 2018 to May 2019 |
3 |
Regulatory Permitting
|
August 2018 to October 2019 |
4 |
Public/Stakeholder Involvement
|
Ongoing with large emphasis during the preliminary design and permitting tasks. |
Phase 1 Schedule: Study
Task | Description | Timeframe |
---|---|---|
1 | Study Work Plan & Public Outreach Plan Development, Data Collection, Criteria Development | March 1 to mid-May, 2017 |
2 | Analysis of Existing Conditions | April to mid-June, 2017 |
3 | Alternatives Development & Evaluation | Mid-June to September, 2017 |
4 | Finalization of Study & Reporting | September to February, 2018 |