1 |
Data Collection
- Kickoff Meeting
- Existing & New Data Collection
- Site Assessments — dam, wetlands, erosion areas on lake, Thorofare
- Design Recommendations — refinement of recommendations from Phase 1 and any new information gathered that could affect the scope of preliminary design
- Basis of Design — refinement and update from Phase 1
- Steering Committee Meeting #1 — late August
|
July to August, 2018 |
2 |
Preliminary Engineering Design
- Regulator Agency & Stakeholder Engagement
- Steering Committee Meeting #2 — November 2018
- Public Meeting/Open House — late September 2018
- Permitting Level Plans — draft March; final April
- Updated Construction Cost Estimates — draft April
- Dam Improvements & Dam Safety Report Submittal — includes discipline reports (geotechnical, structural, hydraulic, and so forth) — March
|
September 2018 to May 2019 |
3 |
Regulatory Permitting
- Consultation with Agencies regarding proposed concepts — September 2018
- Permit Application Documents — initiate development of documents starting in September and working through Spring 2019
- Permit Application Submission — Spring 2019
|
August 2018 to October 2019 |
4 |
Public/Stakeholder Involvement
- Steering Committee Meeting #1 — late August 2018 (in person)
- Steering Committee Meeting #2 — mid-September 2018 (telecon)
- Public Meeting/Open House — late September 2018 (in person, Priest Lake)
- Steering Committee Meeting #3 — October 2018
- Steering Committee Meeting #4 — November 2018
- Steering Committee Meeting #5 — July 2019
|
Ongoing with large emphasis during the preliminary design and permitting tasks. |